Contract #18-021
Construction of The Hillside Avenue Green Infrastructure Demonstration Project is scheduled to begin the week of March 26, 2018. The project area is the west side of Hillside Avenue between Admiral Kalbfus Road and Beacon Street. The project includes installation of bioretention gardens in the sidewalk esplanade; installation of permeable block pavers in the parking stalls adjacent to Miantonomi Memorial Park; and installation of underdrains, and improvements to sections of storm drain, manholes, and catch basins in the southbound lane of Hillside Avenue. D’Allessandro Corporation will mobilize for construction the week of Monday, March 26, 2018. The project is scheduled for completion by June 29, 2018. The general sequence of construction is as follows (dates are tentative):
Construction mobilization, test pits, setup, and delivery of materials (Tuesday, March 27).
Improvements to storm drain, manholes and catch basin in south bound lane of Hillside Avenue (Monday, April 9).
Installation of bioretention basins, tree box filter, and underdrain,
Installation of permeable brick paver parking areas.
Landscaping, loam and seed, project cleanup.
Project Completion (Friday, June 29, 2018).
Completed August 2015